Medium Voltage 11kV Cable Joint Demonstration

Remove 1 meter of the Red [Oversheath];to expose the [Armouring] – Single Layer of galvanised circular steel wires – to be cut away.

Insert collar under the [Armouring] and tighten with external collar.

Remove black [Sheath], [Tape Binder], white[Laying up] to expose the copper[Metallic Screen].

Remove black insulation Screen to expose grey insulation.

Repeat for 2nd Cable.

Expose 10cm of the conductor, clean, add insulation and prepare for insulation test.

Insulation test before mechanical connection of cable conductors.

IMG_6265

Remember to insert the final Oversheath in the last step before you joint the cable.

Mechanical joint of conductors, with heat shrink insulation and wrap over with braiding tape.

Wrapping of Armouring steel guard wire and testing insulation.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s